MDA report after official visit SEDAPAL
To Remember I present the official diagnosis of SEDAPAL after his visit to the city of Ilo. No comments.
Report N ° 087-2008-GCR-PEy
A: PROJECT TEAM LEADER
Ing ° Marc Cerrone Palomino
Subject: ILO Business Dialogue Roundtable
"Plant Wastewater Treatment of the Province of Ilo.
Reference: O / Mn · 097-2008-PCM/SC PEy Reg No. 4441 (SG 6206)
Date: Lima, 24 September
2.008
hereby, I have to kindly inform you, regarding the visit to the city of Ilo, in accordance with the Charter Indicated N ° 179-2008-GPO, dated 06.09.2008, whereby the Project and Construction Management I SEDAPAL designated representative to to make a presentation on technologies Treatment Plant domestic wastewater regard we state the following;
1 .- GENERAL.
The visit to the city of Ilo was performed according to schedule, being on 17 September, which saw the first instance to the Office of the Environment of Southern Peru, which was carried out preliminary meeting on the working agenda of the day, with the following: Participants
Ms. Maritza Perca Civil Society - MDA ILO
Ing ° Alejandro León Civil Society - MDA ILO
Ing ° Dario Oviedo Southern Peru
Ing ° Jorge Guzman Manager ILO General
EPS Ing ° Cesar Yana EPS Operations Manager ILO
Agenda
EPS guided tour of the ILO, for the presentation of the diagnosis of your water system and sewage treatment plant
water (Pasto Grande and Ite)
pumping stations and reservoirs
plant wastewater treatment
SEDAPAL representative exhibition on technologies for the treatment of domestic sewage.
On the other hand noted that the City of Ilo, there is a pre-investment study at profile No. 56001 "Construction and Implementation of a Wastewater Treatment in Ilo City "as an alternative solution having an Activated Sludge System (Extended Aeration)
2 .- ANALYSIS OF THE TOUR
Referring to the Treatment System of Wastewater drains are Ilo City led to a Treatment Plant oxidation ponds, which has a pretreatment system (bars and sand trap chamber and flow meter) then go to a primary lagoon, then to a battery of two secondary lagoons (one inoperable) and finally a battery of two tertiary lagoons (one inoperable), with the final discharge to the sea. Gaps initially operated with a mechanical system "ventilators" working as aerated lagoons, but the high costs of operating and maintaining the EPS, said that has not been able to maintain this equipment being removed from the treatment plant. Also
WWTP has no perimeter fence, a bed of dried sludge, laboratories, offices, equipment storage, security towers, lighting, finally the operators do not have a manual for the proper operation and maintenance of WWTP. 3.-
TECHNOLOGY EXHIBITION SYSTEM DOMESTIC WASTEWATER TREATMENT
The aim of the exhibition is to present the different technologies SEDAPAL used to treat wastewater from Lima and Callao, in order to protect public health, improve the quality of life of the people and preserve the environment.
Unveiling the following technologies and the advantages and disadvantages:
Anaerobic System - Aerobic
Carapongo
WWTP WWTP WWTP José Gálvez
San Pedro de Lurin
Activated Sludge - Extended Aeration WWTP
Puente Piedra
WWTP San Antonio de Carapongo
New Headquarters WWTP Atarjea
Aerated Lagoons San Bartolo
WWTP WWTP WWTP San Juan
Huáscar
Lagunas Oxidation
Window WWTP WWTP WWTP Ancon
July C Tello
4 .- CONCLUSIONS AND RECOMMENDATIONS
It is necessary to consider any technology to be chosen for the treatment system of wastewater from the City Ilo is important to ensure its sustainability, ie their operation and maintenance preserves that this implies, akin to ensure the smooth operation of the WWTP.
The ILO EPS has to be considered a business opportunity that downstream of the WWTP is located industry "Southern Peru" which requires water for the operation of the industry processes for it would treat the wastewater according to the application that requires the industry.
The study achieved and declared viable "Construction and Implementation of a Water Treatment Plant in the city of Ilo" in order to reduce the risk, having more approximate costs and optimize the proposed design, we propose to consider, if possible to develop a project to study at, in order that they may have more raw data, mean pre-level plans for infrastructure design and profile projected plant, equipment, technical specifications, as well as complementary studies, soil topographic, budgets, which must be developed by a specialist, a sanitary engineer.
Sincerely, Ing ° Renso
García Box
Senior Project Engineer
With the agreement of this report go to Project and Construction Management for its knowledge and goals. Sincerely
Cerron Ing ° Marco Palomino
Wednesday, September 24, 2008
Wednesday, September 17, 2008
Mouth Soft Palate Abscess
Steps to visit officials Ilo
According to the issues raised in the House of Ilo MDA Technical Committee meetings in their proposed topics for the officials to visit us:
-Theme SUNASS official: Situational diagnosis for drinking water solution wastewater treatment in the province of Ilo "
-Theme SEDAPAL official:" Exposure of the different technologies to solve the drinking water and wastewater treatment in the province of Ilo.
The agenda is:
- Visit Guided
- Exhibition
- Conclusions and recommendations
The DGGS of MINEM was coordinating with:
Sedapal: Project and Construction Management - Ing Ana Coletti
Sunass: Management Oversight and Control - Mabel Ing
Morillo The 2 managers have agreed to ask them to reach the Project Profile Treatment Plant wastewater Ilo and the executive summary will be sent via
email the information on the draft presented by the Mayor of the MPI (SNIP Code 56001: Construction and implementation of a system of wastewater treatment in the city of Ilo, amount: S /. 23,258,392.10).
was sent the profile of this project that appeared in the doorway of MEF in relation to PIP 56001.
an Executive Summary In addition to the problem of drinking water and wastewater treatment in the province of Ilo :
Approximate population: 70,000 HBTS.
Water comes to the Province of Ilo from two sources: Pasto Grande and Ite. Water supply
: Pasto Grande (250 l / s), Ite (150 l / s). Total water
: 800 m3 / h
drinking water treatment: Pasto Grande (60 l / s), Ite (500 l / s).
Water supply is rationed (Case of Pampa Wireless is 3hrs every three days).
wastewater treatment, was made using the oxidation ponds, which collapsed and all sewage is deposited directly several years at sea without any treatment.
Morillo Mabel Ing Viera, Director of Monitoring and Control (e) Superintendence of Sanitation Services (SUNASS) requested the ILO EPS is present at the meeting and present an assessment of their drinking water systems and sewage.
addition requested that he forward the Descriptive Report of the WWTP project to Southern plans to finance and, if possible, the conditions of the financing. because unfortunately the Profile tab projects SNIP bank has little information (only present the basic data for the purposes of registration of the project to obtain your code snip).
They sent the request and after some dead ends on the date of travel (12 SET 08) and sending emails are managed to make the visit of Eng º Renso Box Garcia of Project Management and Construction of SEDAPAL for Today Wednesday, 17 September 2008.
The venue was Environmental Services Company SPCC.
Met set the agenda for which was coordinated with the MPI to enable the Manager of the ILO EPS will give us the facilities to visit their facilities.
The tour went to the Company EPS-Ilo for submission of diagnosis of the water system and sewer, then treatment plants catacat drinking water (Ite and Pasto Grande) and the Pampa Wireless ( Pasto Grande), the plant wastewater treatment (Media Luna) and pumping stations and reservoirs.
Throughout the tour were the questions that were answered fully. Then
Eng º Renso García Box made the presentation on different types of technologies that has Sedapal in the city of Lima, in addition to the terms of reference of some sanitation projects. Ing º
Box García promised to send us your comments and suggestions. He was given the part of the EPS Ilo, a ring with the diagnosis and projects implemented in performance and those that require funding. Also, the document scanning project activated sludge.
regret that SUNASS officials were unable to come to this working visit.
According to the issues raised in the House of Ilo MDA Technical Committee meetings in their proposed topics for the officials to visit us:
-Theme SUNASS official: Situational diagnosis for drinking water solution wastewater treatment in the province of Ilo "
-Theme SEDAPAL official:" Exposure of the different technologies to solve the drinking water and wastewater treatment in the province of Ilo.
The agenda is:
- Visit Guided
- Exhibition
- Conclusions and recommendations
The DGGS of MINEM was coordinating with:
Sedapal: Project and Construction Management - Ing Ana Coletti
Sunass: Management Oversight and Control - Mabel Ing
Morillo The 2 managers have agreed to ask them to reach the Project Profile Treatment Plant wastewater Ilo and the executive summary will be sent via
email the information on the draft presented by the Mayor of the MPI (SNIP Code 56001: Construction and implementation of a system of wastewater treatment in the city of Ilo, amount: S /. 23,258,392.10).
was sent the profile of this project that appeared in the doorway of MEF in relation to PIP 56001.
an Executive Summary In addition to the problem of drinking water and wastewater treatment in the province of Ilo :
Approximate population: 70,000 HBTS.
Water comes to the Province of Ilo from two sources: Pasto Grande and Ite. Water supply
: Pasto Grande (250 l / s), Ite (150 l / s). Total water
: 800 m3 / h
drinking water treatment: Pasto Grande (60 l / s), Ite (500 l / s).
Water supply is rationed (Case of Pampa Wireless is 3hrs every three days).
wastewater treatment, was made using the oxidation ponds, which collapsed and all sewage is deposited directly several years at sea without any treatment.
Morillo Mabel Ing Viera, Director of Monitoring and Control (e) Superintendence of Sanitation Services (SUNASS) requested the ILO EPS is present at the meeting and present an assessment of their drinking water systems and sewage.
addition requested that he forward the Descriptive Report of the WWTP project to Southern plans to finance and, if possible, the conditions of the financing. because unfortunately the Profile tab projects SNIP bank has little information (only present the basic data for the purposes of registration of the project to obtain your code snip).
They sent the request and after some dead ends on the date of travel (12 SET 08) and sending emails are managed to make the visit of Eng º Renso Box Garcia of Project Management and Construction of SEDAPAL for Today Wednesday, 17 September 2008.
The venue was Environmental Services Company SPCC.
Met set the agenda for which was coordinated with the MPI to enable the Manager of the ILO EPS will give us the facilities to visit their facilities.
The tour went to the Company EPS-Ilo for submission of diagnosis of the water system and sewer, then treatment plants catacat drinking water (Ite and Pasto Grande) and the Pampa Wireless ( Pasto Grande), the plant wastewater treatment (Media Luna) and pumping stations and reservoirs.
Throughout the tour were the questions that were answered fully. Then
Eng º Renso García Box made the presentation on different types of technologies that has Sedapal in the city of Lima, in addition to the terms of reference of some sanitation projects. Ing º
Box García promised to send us your comments and suggestions. He was given the part of the EPS Ilo, a ring with the diagnosis and projects implemented in performance and those that require funding. Also, the document scanning project activated sludge.
regret that SUNASS officials were unable to come to this working visit.
Friday, September 5, 2008
What Kind Of Hair Does Lauren Londan Use
Plenary Meeting of Ilo MDA
Today Friday 05 September 2008, at the premises of the District Municipality of Pacocha at 4:15 pm met members of the Roundtable Expanded Ilo (MDA) with the presence of Mr. José Luis Carbajal Briceño, Director General of the General Social Management of the Ministry of Energy and Mines, Ms. Sandra Tovar Castro General Office Social Management of the Ministry of Energy and Mines, Mr. Juan Manuel Figueroa Quintana, Secretary of Coordination of PCM, Miss Maria del Carmen Castillo Tagle, Dispute Prevention Unit of PCM, Mrs. Elva Valdivia Davila, Mayor of the District Algarrobal Mr. Arturo Aragon Cornejo, Pacocha District Mayor, Mr. Jorge Mendoza Perez, Ilo Provincial Mayor, Mr. Leonel Villanueva Ticona, Moquegua Regional Director, Mr. Carlos Marin Caceres, Ilo Sub-Region, Ms. Maritza Perea Ortega, Palomino and Mr. Alejandro Leon Walter Delgado Condori, Civil Society representatives, Mr. William Torres Pino, Rodolfo Vicetti Valverde, Manuel Sierra López, Darío Calderón and Mr. Cesar Oviedo Montes de Oca Diban, representatives of the Southern Peru and the presence of Mr. Hector Chavez Cuba, representative of the Ombudsman as an observer the dialogue process.
To that end, Mr. Representative of the Ministry of Mines proceeded to give the welcome to all participants and the press. Later
proceeded to set the agenda for this meeting wing, indicating that they are invited to join the end of it to let them know the resolutions adopted.
After that, we proceeded to develop the agreed agenda items. On each point indicates the following:
1. On the results of the Dialogue Table prepared by the Executive Committee, the Provincial Mayor said he had prepared a report thereon and delivered written minutes of Executive Committee meeting on 25th August 2008.
2. On the coordination with and SEDAPAL SUNASS.
the coordianciones been made with both institutions and have requested information about the project Plant Wastewater Treatment. It is collecting the information requested by them then, the Ministry of Energy and Mines and the Provincial Municipality of Ilo continue with the coordination for technical visit to the city of Ilo, noting tentative date next Friday September 12 2008.
3. On the system of monitoring air quality in the city of Ilo. Ms. Noelia Hinojosa
the Provincial Municipality of Ilo said that next week's visit will take place the company that installed the current monitoring station in the municipality. After this visit will be the respective report. Tentative date is noted on Tuesday, 09 September 2008 for the realization of a coordination meeting between the Municipality technicians, the company that installed the monitoring station and from the Southern to define the realization of this system.
4. On the treatment of drinking water and wastewater from the open woodland.
be requested documents on the Ilo EPS report that analyzes the best treatment option for the district of El Algarrobal. These documents will entega to the Executive Committee and Technical Committee for their information.
With the involvement of all members and on their consensus to take the following resolutions:
1. The Executive Committee shall draw a proposed draft of what would be the Framework Convention for additional funding of projects that are prioritized in the Bureau, in accordance with the agreement number 6 on the previous session.
2. The Southern and the Provincial Municipality of Ilo presented at the next meeting an executive report on the development of the work of water supply and drainage Pacocha District.
3. Hold the next meeting on Friday, October 3, 2008 at 4:00 pm at the premises of the District Municipality of Pacocha, with the agenda and reports of the Technical and Executive Committees. After
signed the Minutes of the meeting invited the press to give them information on the arrangements and answer all questions.
Today
Today Friday 05 September 2008, at the premises of the District Municipality of Pacocha at 4:15 pm met members of the Roundtable Expanded Ilo (MDA) with the presence of Mr. José Luis Carbajal Briceño, Director General of the General Social Management of the Ministry of Energy and Mines, Ms. Sandra Tovar Castro General Office Social Management of the Ministry of Energy and Mines, Mr. Juan Manuel Figueroa Quintana, Secretary of Coordination of PCM, Miss Maria del Carmen Castillo Tagle, Dispute Prevention Unit of PCM, Mrs. Elva Valdivia Davila, Mayor of the District Algarrobal Mr. Arturo Aragon Cornejo, Pacocha District Mayor, Mr. Jorge Mendoza Perez, Ilo Provincial Mayor, Mr. Leonel Villanueva Ticona, Moquegua Regional Director, Mr. Carlos Marin Caceres, Ilo Sub-Region, Ms. Maritza Perea Ortega, Palomino and Mr. Alejandro Leon Walter Delgado Condori, Civil Society representatives, Mr. William Torres Pino, Rodolfo Vicetti Valverde, Manuel Sierra López, Darío Calderón and Mr. Cesar Oviedo Montes de Oca Diban, representatives of the Southern Peru and the presence of Mr. Hector Chavez Cuba, representative of the Ombudsman as an observer the dialogue process.
To that end, Mr. Representative of the Ministry of Mines proceeded to give the welcome to all participants and the press. Later
proceeded to set the agenda for this meeting wing, indicating that they are invited to join the end of it to let them know the resolutions adopted.
After that, we proceeded to develop the agreed agenda items. On each point indicates the following:
1. On the results of the Dialogue Table prepared by the Executive Committee, the Provincial Mayor said he had prepared a report thereon and delivered written minutes of Executive Committee meeting on 25th August 2008.
2. On the coordination with and SEDAPAL SUNASS.
the coordianciones been made with both institutions and have requested information about the project Plant Wastewater Treatment. It is collecting the information requested by them then, the Ministry of Energy and Mines and the Provincial Municipality of Ilo continue with the coordination for technical visit to the city of Ilo, noting tentative date next Friday September 12 2008.
3. On the system of monitoring air quality in the city of Ilo. Ms. Noelia Hinojosa
the Provincial Municipality of Ilo said that next week's visit will take place the company that installed the current monitoring station in the municipality. After this visit will be the respective report. Tentative date is noted on Tuesday, 09 September 2008 for the realization of a coordination meeting between the Municipality technicians, the company that installed the monitoring station and from the Southern to define the realization of this system.
4. On the treatment of drinking water and wastewater from the open woodland.
be requested documents on the Ilo EPS report that analyzes the best treatment option for the district of El Algarrobal. These documents will entega to the Executive Committee and Technical Committee for their information.
With the involvement of all members and on their consensus to take the following resolutions:
1. The Executive Committee shall draw a proposed draft of what would be the Framework Convention for additional funding of projects that are prioritized in the Bureau, in accordance with the agreement number 6 on the previous session.
2. The Southern and the Provincial Municipality of Ilo presented at the next meeting an executive report on the development of the work of water supply and drainage Pacocha District.
3. Hold the next meeting on Friday, October 3, 2008 at 4:00 pm at the premises of the District Municipality of Pacocha, with the agenda and reports of the Technical and Executive Committees. After
signed the Minutes of the meeting invited the press to give them information on the arrangements and answer all questions.